03.08.2021

A film documenting the last months of the construction of the Warszawa Zachodnia station

Share article

The construction site of the Warszawa Zachodnia station currently employs 680 people (although it has already exceeded 2,600 people brought to the construction site), 75 subcontractors and subcontractors , and 160 equipment units.

At the moment, the work is ongoing:

– Execution of tunnel floor slabs in segment 3 and 4 (under platforms 8, 7 and 6).

– Reinforced concrete works and excavations on segment 1 of the tunnel (area of the ring line).

– Masonry, insulation and installation works on a multifunctional building.

– Construction works on the roof of the platform hall in the western part of the station, platforms 6 and 7.

– Undergrade, track, SRK and traction works on the western part of the station and subgrade works on the entire track 2 at platform 6.

– Engineering works in the tunnel of Aleja Prymasa Tysiąclecie (western aisle). Engineering works on retaining walls No. 1 and 2.

– Installation of bearings on the footbridge over the platforms.

– Platform works with internal installations on platforms 6 and 7 in the eastern part of the station.

– Construction of sector shelters on platforms 6, 7 and 8.

– Installation works on retention reservoirs