Home > Biskupia Górka in Gdańsk is almost halfway through
Find in media:
Menu
About us
Offer
Electromobility
Foreign markets
We are reaching out further and further. We are making strategic investments outside Poland.
News
Contractors
Investor relations
Investor information
Current quotes
See moreFinancial ratios
Current quotes
See moreESG
Safety
This is our priority and our common good. We are committed to ensuring that our employees and partners, once the work is completed, return home safely.
Media
About everything we do.
On a regular basis.
Find in media:
16.07.2019
Works on the construction of a new viaduct at Biskupia Górka in Gdańsk are already close to the halfway point. The construction of the first of two arched viaducts over the railway tracks towards Gdańsk Główny is already ready.The paving will begin soon. This will allow temporary traffic to run the new viaduct and at the same time enable the demolition of the old viaduct –says Site Manager Michał Radziszewski.
The biggest challenge of this contract is its location. The new road system will be built on 800 meters of national road No. 91 at the level of Biskupia Górka, the SKM Śródmieście stop and the Pomeranian Voivodeship Office. It is a particularly sensitive place where traffic from Pruszcz Gdański flows into the centre of Gdańsk and connects with the national road No. 7 towards Warsaw. At the same time, we carry out all bridge works over rail traffic without stopping trains – says Damian Kryszewski, Contract Director.
In connection with the archaeological findings considered by the Conservator of Monuments as worthy of being exhibited as monuments of history, the construction of the car park and its surroundings will be implemented in such a way as to create not only functional possibilities for the user, but also to please the eye of visitors.
In addition to the historic downtown development and the need to carry out work on active railway lines, the biggest challenge in terms of engineering and organization is still ahead of us, is the demolition of the existing bridge structure.In a nutshell, the existing viaduct will be cut in the middle of the span, prestressed with an additional structure, and then pushed beyond the tracks, and there we will safely remove both parts of the viaduct – said Damian Kryszewski, Contract Director on behalf of Budimex SA.
The works are advanced in approx. 40%. The contract worth PLN 147 million is being implemented by Budimex. The investor is the Gdańsk City Hall The planned completion of the works today is October 2020.
Photos:
BGórka3 – the first of two new viaducts
Bgórka1 – Railway line No. 9 running under the viaduct – trains slow down to 30 km/h at this point
Bgórka2 – A fragment of the new flyover and viaduct – on the right side, the place where the underground car park will be built. Archaeological finds are also visible in the trench.