Contact us!
Contact information for the person responsible for the communication
Menu
About us
Offer
Electromobility
Foreign markets
We are reaching out further and further. We are making strategic investments outside Poland.
News
Contractors
Investor relations
Investor information
Current quotes
See moreFinancial ratios
Current quotes
See moreESG
Safety
This is our priority and our common good. We are committed to ensuring that our employees and partners, once the work is completed, return home safely.
Media
About everything we do.
On a regular basis.
Find in media:
01.10.2019
At the construction site of the so-called Yesterday, a “symbolic shovel” was driven into the Łańcut bypass. The contractor for the works is Budimex S.A. The contract for the amount of PLN 115,847,768.51 gross was signed on 18 May 2018. The completion of the investment is scheduled for September 2021.
The extension of national road No. 94 is being carried out in the “optimize-design-build” system. The contractor designed and obtained the decisions required by law. Currently, the Podkarpackie Voivode is conducting the procedure of the amendment issued in 2010. ZRID decision, which is planned to be obtained at the end of October this year. After obtaining the decision, the Contractor will commence the road works in full. “We are currently carrying out preparatory works based on the current decision on the permit for the implementation of the investment to the extent feasible, so that after receiving the amendment to the ZRID decision, we can perform as much work as possible before the winter period,” said Jarosław Jochymek, Contract Director, Budimex S.A.
The contractor is now focusing mainly on the section of DK94 in Głuchów, where the following is ongoing:
>> removal of trees and shrubs with tidying up the area,
>> removing the layer of humus,
>> demolition of the surface,
>> preparation of the area for the implementation of detours,
>> sapper, environmental and archaeological reconnaissance,
>> preparation of access roads to the planned bridge structure,
>> inventories of buildings, roads and areas for the planned gas pipeline,
>> preparation of areas for the storage of materials.
Scope of works
As part of the task, it is planned to leave the cross-section of the national road as a single-carriageway, two-lane (one lane in each direction), with a lane excluded from traffic with a protective barrier, over a length of 5.82 km. The works will consist in replacing the road structure and, where necessary, widening the road body. The works will be carried out while maintaining the continuity of two-way traffic on DK94.
The scope of works also includes the reconstruction of single-level intersections – 5 roundabouts at the intersection of DK 94 with: DW 877, DW 881, ul. Graniczna Street (connector to the A4 motorway), ul. Kościuszki and DP 1520R and the ordinary intersection with ul. Piłsudski. The contractor will also build a road bridge over the Sawa River with a length of 100 km. 33 m, access roads and will rebuild and build technical infrastructure equipment:
>> water, sewage and gas networks, including the reconstruction of the DN400 high-pressure gas network to the length of 6 km,
>> power and telecommunication networks, service duct, lighting,
>> traffic safety devices, noise barriers, vertical and horizontal markings.
Bearing in mind the safety of road users, especially the least protected ones, i.e. pedestrians and cyclists, it is assumed that sidewalks and pedestrian and bicycle paths as well as bus bays will be built.
As part of the design work, the Contractor proposed new solutions, to which applications from local authorities were submitted. GDDKiA, in order to meet the submitted demands, to a large extent took them into account in the replacement construction project.
Examples of changes introduced on the basis of the demands of local governments:
>> the entrance and exit from the areas of: MOSiR, District Hospital, Education Center and Technical School Complex to DK94 to right-turn with the possibility of making a left-turn maneuver has been designed,
>> new bus bays have been designed or the location of existing ones has been changed,
>> new pedestrian crossings have been designed or their location has been changed,
>> a direct connection to DK94 m.in was designed. hive. Bema and ul. Orzeszkowa,
>> a direct connection of the additional roadway to the roundabout in Głuchów was designed due to the location of the Cultural Center and the Voluntary Fire Brigade.
Basic technical parameters of the investment:
>> Road Class: GP
>> Road length: 5.82 km
>> Pavement load: 115 kN/axle
>> Load on objects: Load capacity cl. “A” acc. PN 85/S – 10030 and “Stanag C 150”
>> Cross-section: 1×2
>> Lane width: 3.5 m
>> Traffic load category:KR5
>> Sidewalks: 2.0 m
>> Pedestrian and bicycle routes: 3.5-4.0 m
>> Width of the roadway of access roads: 3.50 – 6.00 m
>> The central part of the roadway is excluded from traffic with bituminous surfaces and cobblestones: 3.5 m
Timeline:
>> Task name:“Continuation of construction with optimization of design solutions for the task entitled. Extension of the national road No. 4 (E-40) Jędrzychowice – Korczowa together with the necessary technical infrastructure, structures and construction equipment section 100 Łańcut – Głuchów km 613+767 to 619+589.86”.
>> Obtaining an environmental decision:1 December 2006
>> Decision of the Regional Director for Environmental Protection in Rzeszów agreeing on the terms of the project: 26 July 2010
>> Obtaining a decision on the permit for the implementation of a road investment (ZRID):29 September 2010
>> Finality of the ZRID decision – 26 November 2013
>> Finality of the environmental decision: 19 January 2017
>> Announcement of the tender for the Contractor of the works: 15 July 2017
>> Signing of the contract with the Contractor: 18 May 2018 (Contractor: Budimex S.A., amount: PLN 115,847,768.51 gross, deadline: 34 months)
>> Announcement of the tender for a Consultant: September 13, 2017
>> Signing the contract with a Consultant: June 15, 2018 (Promost Consulting Sp. z o.o. sp.k.)
>> Submission of an application to amend theZRID decision: 18 March 2019
>> Initiation of proceedings by the Podkarpackie Voivode regarding amendments to the ZRID decision: 23 May 2019