21.08.2012

Budimex will build an access road to the Lublin bypass

Share article

The scope of work includes:

– construction of a 3.8-kilometer  section of the main route Al. Solidarity

– reconstruction of Al. Warszawska along with the distribution of traffic to the road
collective and  distribution, construction of a complex of road junctions at the intersection of Al. Solidarności and Al.  Warszawska and the construction of the Sławin junction,

– reconstruction of the following streets: Główna, Mgielna, Jaśminowa and Wądolna,

– construction of service roads,

– construction of a bicycle and pedestrian route,

– construction of engineering structures:

  • of the road viaduct in the line of ul. Main
  • of the road viaduct in the line of ul. Mist,
  • a road bridge over the Czechówka River,
  • a pedestrian and bicycle bridge over the Czechówka River,
  • two road viaducts in the line of slip roads,
  • a road bridge in the line of two slip roads over the Czechówka River,
  • of the road viaduct in the line of ul. Warsaw
  • road culverts
  • reinforced concrete retaining walls.

– construction of road drainage

– removal of collisions with sanitary and rainwater sewage systems as well as with water and gas supply networks,

– reconstruction of power lines,

– construction of teletechnical infrastructure,

– construction of noise barriers,

– relocation of the watercourse and the Czechówka River,

– construction of traffic lights and planting greenery.

The works will begin within two weeks of signing the contract. At the initial stage of the investment, geological surveys will be carried out, and geodetic works and land inventory will be carried out at the same time. Then the contractor will proceed to cut down trees and remove the fertile layer of soil (humus removal).

The deadline for completion of the works is 30 September 2014.