05.05.2016

Budimex will build the S5 from Leszno to Kaczków

Share article

On 5 May 2016, Budimex signed a contract with the Poznań Branch of the General Directorate for National Roads and Motorways for the construction of the S5 Poznań – Wrocław expressway, Radomicko – Kaczkowo section, stage II from Leszno Południe (with the junction) to Kaczkowo. The contract has a net value of PLN 189.1 million.

The scope of work includes the construction of:

  • 9.5-kilometre section of the S5 expressway (two carriageways with two lanes each),
  • the “Leszno Południe” road junction,
  • 8 engineering structures (one bridge along the S5 road, four road viaducts, one upper passage for animals, two viaducts along the connector, including one over the railway line),
  • culverts, environmental protection devices, road lighting.

The investment also includes the reconstruction of transverse and access roads and the reconstruction of collisions.

The construction of the S5 expressway will take 20 months, and the winter periods from 15 December to 15 March will not be included in the time of implementation of the investment.