20.06.2017
Budimex S.A. informs that in connection with the commencement of construction works on the construction contract for Czerniakowska Bis (Al. Polish Walczej) on 20 June 2017 from 10 a.m. 1:00 p.m. at ul. J. Nehru introduces changes in traffic organization – stage 1.
The contractor will start the demolition of 12 commercial buildings and works related to the reconstruction of the heating network in this area.
Changes in traffic organization will consist in the closure of the northern roadway of ul. J. Nehru on the section from ul. Zwierzyniecka to ul. Czerniakowska.
Vehicle traffic will take place on the southern roadway in both directions, and pedestrians will move only on the pavement on the southern side of ul. J. Nehru.
The planned period of closure of the northern roadway of ul. J. Nehru – from 20.06.2017 to 10.07.2017.
After the completion of stage No. 1, temporary traffic organization will be introduced – stage 2.
We will inform you about the temporary traffic organization at stage 2 at a later date.