19.11.2020
The construction works carried out by Budimex on the construction of the Wałbrzych bypass are 65% advanced. Approx. 350 people and 170 equipment units were involved in the implementation of m.in. earthworks and surface works, paving works, rainwater drainage and road lighting.
On the so-called The old part of the bypass is underway to install noise barriers. A structure of gabion baskets on slopes is also being made. On the ES/Z/5 flyover, the right roadway of the carrying structure has been concreted, while the left thread is in the process of formwork and reinforcement. The left retaining wall made of gabion baskets reaching the flyover has been made in its entirety, the right side is under construction.
Advanced paving works are underway at the TESCO roundabout. Nearby, on the right roadway, ul. Łączyńskiego Street, soil stabilization is being carried out for future surface works. The viaduct at ul. The yard in the field of reinforced concrete and asphalt works is 100% complete. Currently, the installation of energy-absorbing barriers is underway and the installation of elements of noise barriers will begin soon. The footbridge located at ul. St. Kinga is 98% complete, the initial flight of stairs with a height of 100 mm remains to be made. 1.5 m and the installation of the remaining barriers.
In selected places, the need to make changes to the construction design, which is beyond the responsibility of the general contractor, has been holding back the progress of work for a long time. This is the case at the height of ul. Reja, Grunwaldzki Square, or the intersection of ul. Starachowicka and ul. Żeromski.
The Wałbrzych bypass is an important project from the perspective of the city’s residents. The road will improve the comfort and speed of communication to workplaces, schools and public facilities. The Wałbrzych bypass has been under construction since last year. Year. The contract deadline for the completion of the works is June 2021, and the net value of the investment is PLN 249,637,589.90.