21.08.2015

Two bids from Budimex selected in the tender for the construction of the S17

Share article

On 21 August 2015, the Lublin Branch of the General Directorate for National Roads and Motorways announced the selection of two bids from Budimex for the design and construction of two sections of the S17 Garwolin – Kurów expressway: from Garwolin to Gończyce (PLN 234.6 million net) and from Gończyce to the border of the Lubelskie and Mazowieckie voivodeships (PLN 255 million net).

The sections have a total length of 25.2 km – from Garwolin to Gończyce – 12.2 km and from Gończyce to the border of the voivodeships – 13 km.

The over 25-kilometer section of the expressway will have two roadways with two lanes each. The construction of the S17 also includes the construction of engineering structures and accompanying infrastructure. As part of the construction of the section from Garwolin to Gończyce, Budimex will also build:

  • two road junctions,
  • access and technological roads,
  • 10 engineering structures along the expressway and over the expressway,
  • 2 road structures along access roads over watercourses,
  • Motorway Service Area and Expressway Maintenance Circuit.

On the section from Gończyce to the border of the Mazowieckie and Lubelskie voivodeships, Budimex will build:

  • one road interchange,
  • access and technological roads,
  • 13 engineering structures along the expressway and over the expressway,
  • 5 road structures along access roads over watercourses,
  • Passenger service area.

Budimex will have 34 months from the signing of the contract to implement the investment. Winter periods from 15 December to 15 March will not be included in the implementation time.