Construction of the S5 and S10 expressways. Stryszek junction – Białe Błota junction

Construction of the S5 and S10 expressway on the section Stryszek junction – Białe Błota junction with a length of 10.4 km. As part of the investment, two new roadways of the S5 expressway were built, which will replace the existing single-space roadway. Thus, access roads were created, necessary for the proper functioning of the S5 and S10 roads. Culverts, a rainwater drainage system and road lighting were also made for this investment. The water supply system, sanitary sewage system, telecommunications, power engineering, railway traction and drainage facilities were also rebuilt. The net value of the project amounted to PLN 309 million and exceeded 10% of Budimex SA’s equity.