Czeczów-Kiełczów gas pipeline (Lower Silesia)
As part of the investments carried out in Lower Silesia, we have built 32.5 km of high-pressure gas pipeline. The section led from ZZU Czeszów to the Kiełczów junction. In addition to laying the pipes themselves, the project also involved the construction of linear shut-off and relief systems with bypass systems in the area of Miłonowice and at the Kiełczów gas hub. In cooperation in a consortium with Mostostal Kraków SA (Partner), we made 28 trenchless crossings over terrain obstacles using jacking, drilling and microtunneling in DN 1200 and DN 1400 casing pipes and 2 crossings of valuable natural areas – using the horizontal directional drilling (HDD) method with a total length of 1250 m. The scope of the project also included gasification and commissioning of the gas pipeline.
Project value: PLN 63.7 million net