Budimex will build over 70 km of the S10 route in West Pomerania

Udostępnij artykuł

Budimex S.A. wins tenders for key sections of the S10 Szczecin – Piła road

Budimex’s bids for 5 key sections of the S10 Szczecin – Piła expressway were considered the most advantageous by the contracting authority: the General Directorate for National Roads and Motorways  , Szczecin Branch. The total length of these sections will be 74 kilometres, which is over 70% of the length of the new expressway from Stargard Szczeciński to Piła. The investment will be implemented in the Design and Build formula.

Over 100 km of new expressway

The S10 will be a dual carriageway expressway with two lanes in each direction. The decision on environmental conditions issued in July last year is final and determined the route of the route. The new S10 expressway will bypass the towns through which the current DK10 runs, including Suchań, Recz, Kalisz Pomorski and Mirosławiec. The new route will connect with the already existing Wałcz bypass, and then the S10 will run south of the existing DK10. At the Piła Północ junction – the future connection of the S10 and S11 – the Stargard – Piła section will end. The construction of eleven road junctions is planned along the route. Five pairs of Motorway Service Areas and two Road Maintenance Circuits will also be built.

From Szczecin to Toruń in 2023

The S10 road, approx. 410 km, will connect Szczecin via Piła, Bydgoszcz and Toruń with the Warsaw agglomeration. The implementation of all missing sections is included in the Government Programme for the Construction of National Roads until 2030. It will be a direct connection between the regions of Western Pomerania, the north of Wielkopolska, Kuyavian-Pomeranian and Mazovia. Thanks to this road, an alternative transport route will be created north of the A2 motorway.

Budimex submitted the most advantageous bids for the following sections:

Section 8: Witankowo Interchange – Piła Północ Interchange – 13 km

Offer value: PLN 586,422,080.00 net

Date of commencement of works: from the date of conclusion of the contract by both parties

Date of completion of works: 39 months from the date of conclusion of the contract (winter periods are not included in the time of completion of works)

Warranty period for major works: up to 15 years

Warranty period: 60 months from the date indicated in the Takeover Certificate

Section 7: Piecnik – Wałcz Zachód – 16 km

Date of information: 19.02.2024

Offer value: PLN 448,960,288.00 net

Completion date: 39 months from the date of conclusion of the contract, excluding winter periods

Warranty period: up to 15 years, warranty period: 60 months

Section 6: Łowicz Wałecki Junction – Piecnik Junction – 15 km

Value of the offer: PLN 437,439,230.00 net

Completion date: 39 months from the date of conclusion of the contract, excluding winter periods

Warranty period: up to 15 years, warranty period: 60 months

Section 5: Cybowo Junction – Łowicz Wałecki Junction – 16 km

Value of the offer: PLN 492,089,901.00 net

Completion date: 39 months from the date of conclusion of the contract, excluding winter periods

Warranty period: up to 15 years, warranty period: 60 months

Section 2: Stargard Wschód junction – Suchań junction – 14 km

Offer value: PLN 366,166,760.93 net

Date of commencement of works: from the date of conclusion of the contract by both parties

Date of completion of works: 39 months from the date of conclusion of the contract (winter periods are not included in the time of completion of works)

Warranty period for major works: up to 15 years

Warranty period: 60 months from the date indicated in the Takeover Certificate

Budimex S.A.’s bids were rated the highest in tender procedures, which proves trust and recognition of the company’s experience and competence in the implementation of large infrastructure projects. It should be noted that despite the high evaluation of the offers, the tender procedures for the evaluation of the offers have not yet been finally completed.