17.10.2013
Until the completion of the construction of the city stadium at ul. Krochmalna Street in Lublin, and the level of progress of works exceeded 50 percent.
There are still works to be carried out that Budimex will be able to carry out in the winter. Currently, the construction of the roof over the stadium is being made.
Over the club and conference part of the stadium, the roof is being insulated. The total area of insulation is 3.2 thousand. m.kw. Aluminium window and door joinery is being installed, as well as facades for glazing.
The installation of electrical, sanitary and ventilation systems is underway. Masonry and plastering works have also begun. Inside the facility, the stands are being sealed and these works will last until the end of October.
A parking lot for 1100 cars is being built outside. Reinforced concrete works on the retention reservoir are coming to an end.
The investment is being carried out in such a way that its continuation is possible also in unfavorable winter conditions.
The contract for the design and construction of the city stadium in Lublin, worth PLN 110.7 million net, was signed on September 2, 2011. The completion of the investment is scheduled for the end of June 2014. The stadium will accommodate 15.5 thousand. Viewers. There will be two presidential boxes and 10 VIP boxes.