Bełchatów Power Plant
At the power plant in Bełchatów, reinforced concrete works were carried out as part of the Order Package No. 2, general construction and finishing works for the 833 MW Unit. The works took place in the main building and in the desulphurization facilities. The concreting of the foundation slab took 138 hours. More than 27 m³ of concrete was poured with an average flow rate of 196.7 m³ per hour. The net value of the project amounted to PLN 150 million.